3773-2 PARAGON MSS1 BALLAST AND SEAWATER SERVICE DOUBLE ISOLATION VALVES SURVEY HEADCAM VIDEO

This walkthrough video familiarisation footage has been captured during a site visit on-board the Paragon MSS1 Semi-Submersible drilling unit, July 2015. The purpose of this site visit was to glean information for the various work scopes planned to be executed during the 2016 Out Of Service period (OOS). This walkthrough video captures the current arrangement of the starboard ballast and seawater service piping immediately downstream of the seachests, it is planned to install a second valve between the seachest and the strainers to provide double isolation. This video will also aid the on shore project team and their contractors during project meeting and briefings.